Newcomb Hall First and Fourth Floor Renovation - Week of October 20, 2025

Sources of Noise

  • Heavy Equipment
  • Demolition
  • Utility Vehicles
  • Power Tools

Utility Shutdowns:

  • None

Deliveries

  • Misc jobsite materials
  • Misc equipment
  • Concrete Trucks

Events for upcoming week

  • Elevator pit form work and concrete pour
  • Masonry infills at elevator shaft
  • Continue installing wall plates and beams at hoistway
  • Underground conduit for new transformer
  • Continue 1st floor electrical layout


Recap of week performed (October 12-18)

  • Continued elevator pit demo
  • Removed basement act where ceiling conflicts arise
  • Continue selective demo at 4th floor
  • Begin wall layout and top track install at 4th floor
  • Continue 1st floor light weight concrete forming and pour
  • Continue installing barriers and walls for IAQ