Associated Project
Sources of Noise
- Heavy Equipment
- Demolition
- Utility Vehicles
- Power Tools
Utility Shutdowns:
- None
Deliveries
- Misc jobsite materials
- Misc equipment
- Concrete Trucks
Events for upcoming week
- Elevator pit form work and concrete pour
- Masonry infills at elevator shaft
- Continue installing wall plates and beams at hoistway
- Underground conduit for new transformer
- Continue 1st floor electrical layout
Recap of week performed (October 12-18)
- Continued elevator pit demo
- Removed basement act where ceiling conflicts arise
- Continue selective demo at 4th floor
- Begin wall layout and top track install at 4th floor
- Continue 1st floor light weight concrete forming and pour
- Continue installing barriers and walls for IAQ