Newcomb Hall First and Fourth Floor Renovation - Week of September 30, 2025

Sources of Noise
-Heavy Equipment
-Demolition
-Utility Vehicles
-Power Tools

Utility Shutdowns:

- None

Deliveries
-Misc jobsite materials
-Misc equipment
-Concrete Trucks

Events for upcoming week

-Installing work on IAQ plan
-Continue selective demo on 1st & 4th floor
-Continue exploratory demo
-Continue MEP make safe
-Continue layout & install of elevator wall plates


Recap of week performed (September 22-September 26)
-Continue MEP make safe
-Begin core drilling for elevator shaft plates
-Continued miscellaneous selective demolition
-Continued IAQ plan work
-Begin hauling materials in & out of construction entrance