Newcomb Hall First and Fourth Floor Renovation - Week of October 6, 2025

Sources of Noise

-Heavy Equipment
-Demolition
-Utility Vehicles
-Power Tools

Utility Shutdowns:

-None

Deliveries

-Misc jobsite materials
-Misc equipment
-Concrete Trucks

Events for upcoming week

-Begin lightweight concrete on 1st floor
-Continue infill at elevator shaft
-Continue selective demo on 4th floor
-Continue layout & install of elevator wall plates
-Begin 1st floor electrical layout


Recap of week performed (October 5 - October 11)
    
-Continue installing barriers and walls for IAQ
-Continue dedmo of HVAC in elevator shaft
-Begin forming new elevator pit
-Continue layout & install of elevator wall plates
-Begin 1st floor electrical layout