Associated Project
Sources of Noise
- Heavy Equipment
- Demolition
- Utility Vehicles
- Power Tools
Utility Shutdowns:
- None
Deliveries
- Misc jobsite materials
- Misc equipment
- Concrete Trucks
Events for upcoming week
- Prepping for Gantry installation
- Begin masonry infills @ elevator shaft
- Continue exploratory @ basement
- Continue non structural framing on 1st & 4th floor
- Continue work @ transformer pad
- Continue wall plate & beam installation @ elevator shaft
- Continue roof work @ elevator shaft
Recap of week performed (November 2-8)
- Began roof work for elevator 11/3
- Began abatement @ elevator pit & 1st floor S wall
- Installing hat channel @ 4th floor
- Removing brick @ new elevator shaft for upcoming steel installation
- Continued installing wall plates & beams @ elevator shaft
- Continued layout & installation of top track & studs @ 1st floor
- Continued work @ transformer pad