Newcomb Hall First and Fourth Floor Renovation - Week of November 10

Sources of Noise

  • Heavy Equipment
  • Demolition
  • Utility Vehicles
  • Power Tools

Utility Shutdowns:

  • None

Deliveries

  • Misc jobsite materials
  • Misc equipment
  • Concrete Trucks

Events for upcoming week

  • Prepping for Gantry installation
  • Begin masonry infills @ elevator shaft
  • Continue exploratory @ basement
  • Continue non structural framing on 1st & 4th floor
  • Continue work @ transformer pad
  • Continue wall plate & beam installation @ elevator shaft
  • Continue roof work @ elevator shaft

Recap of week performed (November 2-8)

  • Began roof work for elevator 11/3
  • Began abatement @ elevator pit & 1st floor S wall
  • Installing hat channel @ 4th floor
  • Removing brick @ new elevator shaft for upcoming steel installation
  • Continued installing wall plates & beams @ elevator shaft
  • Continued layout & installation of top track & studs @ 1st floor
  • Continued work @ transformer pad