Sources of Noise
- Exterior Heavy Equipment operations
- Cement trucks/ dump trucks
- Vehicle movement
- Dumpster activities (deliveries, dumping, compacting, etc)
Utility Shutdowns
- None at this time
Deliveries
- General construction materials (supplies, lumber, etc.)
- Dumpsters
- Concrete
Events for upcoming week
- Continue 3rd and 4th floor joist/ decking demo and repairs.
- Continue 2nd floor lobby subfloor repairs.
- Form N elevator pit walls and pour. Back fill and form Grade beams.
- Begin window removal/ restoration
- Removal of excavation spoils.
- Continue 1st floor underslab interior plumbing work.
- Inspect and pour Electrical duct bank SouthEast Exterior
Recap of week ending Mar 19, 2023
- Complete pile caps, begin forming grade beams, form and pour South Elevator Pit walls.
- Install electrical duct bank conduit at SouthEast exterior from Building to pull box at corner of building.
- Continue 4th floor North and South joist and subfloor demo/ install.
- 2nd floor lobby subfloor repairs, hardwoods demo and store.
- Continue interior under slab utility installation for 1st floor East Central.
- Picardie walk through in preparation for window removal/ restoration.
- Test concrete, monitor interior vibrations.
- MultiVista document underslab work so far.