Richardson Memorial - Week of March 22, 2023

Sources of Noise

  • Exterior Heavy Equipment operations 
  • Cement trucks/ dump trucks
  • Vehicle movement
  • Dumpster activities (deliveries, dumping, compacting, etc)

Utility Shutdowns

  • None at this time

Deliveries 

  • General construction materials (supplies, lumber, etc.)
  • Dumpsters
  • Concrete

Events for upcoming week

  • Continue 3rd and 4th floor joist/ decking demo and repairs.
  • Continue 2nd floor lobby subfloor repairs.
  • Form N elevator pit walls and pour. Back fill and form Grade beams.
  • Begin window removal/ restoration
  • Removal of excavation spoils.
  • Continue 1st floor underslab interior plumbing work.
  • Inspect and pour Electrical duct bank SouthEast Exterior

Recap of week ending Mar 19, 2023

  • Complete pile caps, begin forming grade beams, form and pour South Elevator Pit walls.
  • Install electrical duct bank conduit at SouthEast exterior from Building to pull box at corner of building.
  • Continue 4th floor North and South joist and subfloor demo/ install.
  • 2nd floor lobby subfloor repairs, hardwoods demo and store.
  • Continue interior under slab utility installation for 1st floor East Central.
  • Picardie walk through in preparation for window removal/ restoration.
  • Test concrete, monitor interior vibrations.
  • MultiVista document underslab work so far.