Sources of Noise
- Heavy Equipment
- Demolition
- Utility Vehicles
- Power Tools
Utility Shutdowns:
- None scheduled at this time.
Deliveries
- MEP utility equipment (minimal)
Events for upcoming week
- Development of the Paul Hall Project Documents continues.
- Installation of MEP utilities on the Building 12 roof continues.
- Heavy demolition of building 14 and 16 continues.
- Demolition debris removal will continue.
- The installation and tie-in of new infrastructure items on the building 12 roof continues.
- Building 12 waterproofing continues.
Recap of week performed (Nov 07 – Nov 13, 2021)
- The installation and tie-in of new infrastructure items on the building 12 roof continues.
- All utilities have been disconnected from Building 16 and rerouted to the Building 12 roof.
- Building 16 will be disconnected from Stanley Thomas by the end of this week.
- Building 12 waterproofing has commenced where Building 12 was separated from Building 14.