Sources of Noise

  • Heavy Equipment
  • Demolition
  • Utility Vehicles
  • Power Tools

Utility Shutdowns:

  • None scheduled at this time. 

Deliveries

  • MEP utility equipment (minimal)

Events for upcoming week

  • Development of the Paul Hall Project Documents continues. 
  • Installation of MEP utilities on the Building 12 roof continues. 
  • Heavy demolition of building 14 and 16 continues.
  • Demolition debris removal will continue. 
  • The installation and tie-in of new infrastructure items on the building 12 roof continues. 
  • Building 12 waterproofing continues. 

Recap of week performed (Nov 07 – Nov 13, 2021)

  • The installation and tie-in of new infrastructure items on the building 12 roof continues. 
  • All utilities have been disconnected from Building 16 and rerouted to the Building 12 roof. 
  • Building 16 will be disconnected from Stanley Thomas by the end of this week. 