Associated Project
Sources of Noise
- Heavy Equipment
- Demolition
- Utility Vehicles
- Power Tools
Utility Shutdowns:
- None
Deliveries
- Job trailers
- Misc jobsite materials
- Misc equipment
- Concrete Trucks
Events for upcoming week
- Development of the Paul Hall Project Documents continues
- Continue structural steel 5th floor
- Begin fireproofing 4th floor
- Continue mechanical rough in
- Continue work on Chilled Water & Steam
- Continue framing walls on 2nd & 3rd floor
- Buck Hoist install 8/26
Recap of week performed (August 14th – 20th 2022)
- Poured 5th floor deck 8/17
- Continued fireproofing 3rd floor steel
- Continued overhead rough-in on 1st & 2nd floor
- Continued metal decking on 4th & 5th floor
- Continued work on Chilled Water & Steam
- Continued framing walls on 2nd floor