Paul Hall - Week of August 26, 2022

Sources of Noise

  • Heavy Equipment
  • Demolition
  • Utility Vehicles
  • Power Tools

Utility Shutdowns:

  • None

Deliveries

  • Job trailers
  • Misc jobsite materials
  • Misc equipment
  • Concrete Trucks

Events for upcoming week

  • Development of the Paul Hall Project Documents continues
  • Continue structural steel 5th floor
  • Begin fireproofing 4th floor
  • Continue mechanical rough in
  • Continue work on Chilled Water & Steam
  • Continue framing walls on 2nd & 3rd floor
  • Buck Hoist install 8/26

Recap of week performed (August 14th – 20th  2022)

  •  
  • Poured 5th floor deck 8/17
  • Continued fireproofing 3rd floor steel
  • Continued overhead rough-in on 1st &  2nd floor
  • Continued metal decking on 4th & 5th floor
  • Continued work on Chilled Water & Steam 
  • Continued framing walls on  2nd floor