Sources of Noise
- Power tools
- Chipping Hammer
- Trucks
- Machines
Utility Shutdowns w/ excavation to begin:
- Water:
- Power:
- Chilled
Deliveries
- N/A
Road Closures/Blockages
- N/A
Approved Extended Work Hours
- N/A
Events for upcoming week
- Framing interior walls 4th & 5th floor
- Forming and Pouring walls
- Pouring B2 6th floor east side
- Installing CHW on north side of site
- Pouring slab on grade in A2
- Plumbing rough in on 3rd and 4th floors
Recap of week ending November 13,2021
- Poured A1 east slab
- Steel delivery
- Plumbing rough in on 4th and 5th floor
- Daily wall deliveries