Events for the upcoming week
- Continue site conduit installations.
- Continue site grading.
- Continue North chain wall prep.
- Continue fence post installations.
- Continue Transformer pad prep at Pickleball courts.
- Remove spoils.
- Coordinate SWBNO timing for Water line work.
- General site cleanup.
- Confirm Gas line valve start date by Delta utilities.
Recap of Week ending September 21, 2025
- Remove spoils.
- Construct and backfill Sewer manhole.
- Remove forms and backfill around seating foundation.
- Continue constructing North court Chain wall.
- Air spade Pine tree roots and remove portion of canopy for Utility routing.
- Install perimeter fence posts around Pickleball courts.
- Trench and install conduits for the transformer pad.
- Route conduits for scoreboards and North court cameras.
- Install collar on new fire hydrant at Lowerline St.