Tulane Goldring Tennis Center - Week of September 22, 2025

Associated Project

Sources of Noise
 

  • Construction Vehicles.
  • Dumpsters

Utility Shutdowns
 

  • None at this time.

Deliveries 
 

  • Construction Materials.

Events for the upcoming week

  • Continue site conduit installations.
  • Continue site grading.
  • Continue North chain wall prep.
  • Continue fence post installations.
  • Continue Transformer pad prep at Pickleball courts.
  • Remove spoils.
  • Coordinate SWBNO timing for Water line work.
  • General site cleanup.
  • Confirm Gas line valve start date by Delta utilities.

Recap of Week ending September 21, 2025
 

  • Remove spoils.
  • Construct and backfill Sewer manhole.
  • Remove forms and backfill around seating foundation.
  • Continue constructing North court Chain wall.
  • Air spade Pine tree roots and remove portion of canopy for Utility routing.
  • Install perimeter fence posts around Pickleball courts.
  • Trench and install conduits for the transformer pad.
  • Route conduits for scoreboards and North court cameras.
  • Install collar on new fire hydrant at Lowerline St.

River Level
 

  • 2.8 ft as of 22Sept2025