Tulane Goldring Tennis and Pickleball Courts - Week of October 6, 2025

Associated Project

Sources of Noise

-Construction Vehicles.
-Asphalt breaking activities.

Utility Shutdowns

-None at this time.

Deliveries 

-Construction Materials.
-Concrete trucks.

Events for the upcoming week

-Continue Drive Lane demo.
-Continue South Tennis grandstand curb resteel.
-Gas line Valve removal of Lowerline Street branch toward University Square Buildings.
-Pour Pickleball curb at Leake ave.
-Pour South Tennis stand curbing.
-Finish North chainwall surface.
-Form / add resteel to transformer pad.
-Continue 16” water line relocation excavation.
-Begin Tennis court net foundations and base material installation.

Recap of Week ending October 5, 2025

-Remove spoils.
-Close Drive Lane from the Multispecialty clinic to Leake Avenue.
-Establish pedestrian path from Pine Street lot to U Square buildings.
-Begin demo of drive lane surfacing.
-Set fence poles in North chain wall resteel.
-Cover scoreboards with protective plastic.
-Pour North Court chain wall.
-Excavate around court gas valves.
-Set Hydrant shut off vale at Lowerline Street.
-Discuss gas valve relocations with Delta Gas. On site Oct 6-8 for relocations.
-Fuse 16” HDPE for water line replacement.
-Relocate dumpster for facility use.

River Level

-4. ft as of 06 October 2025