Sources of Noise
- Hand Tools.
- Ski Steer.
Utility Shutdowns
- None at this time.
Deliveries
- Materials.
Events for upcoming week
- Install front canopy.
- Begin routing CO2 Lines throughout building.
- Professional cleaners are scheduled for Monday.
- Core door cylinders.
- Begin painting ceiling drywall.
- Hydroseed site.
- Hang lights in Restroom, Electrical, and CO2 Room.
- Mount Restroom accessories.
Recap of week ending August 16, 2024
- TBES Pressure tested refrigerant lines.
- Hung, taped, and skimmed ceiling drywall in CO2 and Electrical Rooms.
- Pulled control circuit to the existing Freezer Building.
- Card reader mounted and circuit terminated.
- Established final grade.
- Mounted exterior lights.
- Continued electrical trim out.
- Metal trim completed.