Sources of Noise

-Hand Tools.

Utility Shutdowns

-Heating hot water.

Deliveries

-Heating coils, valves, insulation.

Events for upcoming week

-Install heating coils in ducting.
-Test coils and piping once connected. 
-Insulate heating hot water pipes.
-Repair lab ceiling.
-Install new access panels.
-Program RTU’s.
-Clean lab room and penthouse.

Recap of week ending March 7, 2024

-Shutdown heating hot water for two hot taps into the existing 2 ½” line.
-Connected recently routed copper lines to both hot taps.
-Protected floors with Masonite.
-Covered casework with plastic sheets.
-Cut two 3’ x 2’and one 4’ x 4’ drywall ceiling areas to access ducting.
-Mobilized lift into lab space. Used plywood for floor protection.