TNPRC JRHI Phase II - Week of December 8, 2025

Sources of Noise

  • Hand tools.

 

Utility Shutdowns

  • None Scheduled.

 

Deliveries

  • Second squeeze chute delivery expected mid-December.

 

Events for the upcoming week 

  • Continue installing the first delivery of squeeze chutes.
  • Verify pump system with TBES Monday 12-8-25.
  • Install swivels for NHP enrichment swings.
  • Recap of week ending December 5, 2025
  • Lab Products delivered the first (7) squeeze chutes.
  • Started mounting the first delivery of squeeze chutes to the enclosures.