TNPRC JRH1 - Week of November 22, 2024

Sources of Noise
-Hand tools.
Welding machine.

Utility Shutdowns

-None at this time.

Deliveries

-None at this time.

Events for upcoming week

-Remaining squeeze chutes expected onsite this week.
-Mount remaining squeeze chutes.
-Install chute sliding doors.
-Sand welds and cold galvanize exterior enclosures.
-Insulate exterior lixit pipes.
-Create a punch list for the exterior enclosures.

Recap of week ending November 15, 2024

-Mounted seven of twelve squeeze chutes to the interior enclosures.