TNPRC JRH1 - Week of July 19, 2024

Sources of Noise

  • Hand tools.
  • Bobcat.

Utility Shutdowns

  • None at this time.

Deliveries 

  • Materials.

Events for upcoming week

  • Move forward framing the building rough openings.
  • Create a full mockup of building to exterior tunnel interfacing.
  • Complete a working flush system for Vet Med/Architect review.
  • Continue the exterior enclosure modifications.
  • Mockup exterior cage tunnel for Architects review.

Recap of week ending July 12, 2024

  • Vet Med/Architect reviewed squeeze chute mockup.
  • Vet Med/Architect approved building rough open framing.
  • Began installing metal flashing and termination bar at wall joint.
  • Continued HDPE enclosure skirt.  
  • Moved (2) tunnel frames to accommodate post flanges.
  • Started installing flush system plumbing.