Sources of Noise
-Hand tools.
Utility Shutdowns
-None Scheduled.
Deliveries
-Squeeze chute delivery in approximately 120 days.
Events for the upcoming week
-Apply additional Tnemec coating to the exterior enclosure floors.
-Load computer graphics into Building Automation System.
-Continue punch list items.
-Finish cleaning site.
-Open Task List ongoing.
-Upon delivery, mount squeeze chutes to enclosure post.
Recap of week ending September 26, 2025
-Applied final Tnemec coat to building interior.
-Prepped exterior enclosure floors for an additional Tnemec coat.
-Created computer graphics.
-Continued punch list items.
-Open Task List.