TNPRC JRH1 Phase II - Week of September 30, 2025

Sources of Noise

-Hand tools.

Utility Shutdowns

-None Scheduled.

Deliveries

-Squeeze chute delivery in approximately 120 days.

Events for the upcoming week 
    
-Apply additional Tnemec coating to the exterior enclosure floors.
-Load computer graphics into Building Automation System.
-Continue punch list items.
-Finish cleaning site.
-Open Task List ongoing.
-Upon delivery, mount squeeze chutes to enclosure post.

Recap of week ending September 26, 2025

-Applied final Tnemec coat to building interior.
-Prepped exterior enclosure floors for an additional Tnemec coat.
-Created computer graphics.
-Continued punch list items.
-Open Task List.