TNPRC JRH1 Phase II - Week of September 22, 2025

Sources of Noise

  • Hand tools.

Utility Shutdowns

  • None Scheduled.

Deliveries

  • Materials and equipment.

Events for the upcoming week

  • Resume applying Tnemec flooring to the Vestibule and curbs.
  • Continue applying Tnemec flooring to the interior enclosures and hallway.
  • Address punch list items.
  • Continue to adjust and repair as noted in the Open Task List.
  • Finish computer graphic interface for the Building Automation System.
  • Clean site.

Recap of week ending September 19, 2025

  • Applied Tnemec paint to exterior floors, drain basins, and Vestibule.
  • Began applying Tnemec flooring to the interior enclosures.
  • Completed new gate installation and protection barrier above gate.
  • Started making the Building Automation System Graphics.
  • Continued addressing punch list items.
  • Started Commissioning Agents Open Task List.