TNPRC JRH1 Phase II - Week of October 9, 2024

Sources of Noise

-Excavator.
-Skid steer.
-Bore machine.

Utility Shutdowns

-None at this time.

Deliveries

-Materials and equipment.

Events for upcoming week

-Start 6” force main sewer from the tunnel to the wastewater plant.
-Erect building structural steel.
-Continue K Field tunnel road for two-way vehicular traffic.
-Bore gas main in the Breeding Colony.
-Fuse gas pipes at boring pits.
-Continue excavation for new electrical circuit to enclosures.


Recap of week ending October 4, 2024

-Began K Field tunnel road prep for two-way vehicular traffic.
-Began excavating for new electrical circuit to enclosures.
-Continued erecting building structure.
-Poured and finished perimeter walks.
-Wrecked concrete forms.
-Bored gas main in the Breeding Colony.
-Continued concrete cuts for building block outs.