TNPRC JRH1 Phase II - Week of October 20, 2025

Sources of Noise

  • Hand tools.

Utility Shutdowns

  • None Scheduled.

Deliveries

  • Squeeze chute delivery expected late December.

Events for the upcoming week 

  • Address minor open task items discovered during final walk through.
  • Remove dumpster and restroom.

Recap of week ending October 17, 2025

  • Commission agent issued final open task list following site visit.
  • Vet Med, GC, and Design Team performed a final walk through.
  • Bolted prefabricated gate stops to interior enclosure frames.
  • Facilities located enrichment items within enclosures for approval.