TNPRC JRH1 Phase II - Week of June 27, 2025

Sources of Noise
-Hand tools.
-Welding machines.
 

Utility Shutdowns

-None Scheduled.

Deliveries

-Materials and equipment.

Events for the upcoming week

-Install enrichment perches, gates, and detail fencing.
-Follow with insulation and plumbing as cages progress.
-Fabricate the second half of the connection tunnels offsite.

Recap of week ending June 20, 2025

-Passed the St. Tammany final electrical inspection.
-Delivered half of the connection tunnels.
-Squeeze chute minor revisions noted and sent to the manufacturer.
-Continued installing cage enrichment perches.
-Pulled chain fabric, hung gates, and detailed panels.