Sources of Noise
-Man lift
-Skid Steer
-Small excavator
-Hand tools
-Dozer
Utility Shutdowns
-None at this time.
Deliveries
-Materials and equipment.
Events for upcoming week
-Begin floor scarification. Weather permitting, start applying floor system.
-Continue forming concrete curbs for exterior cages.
-Pour/finish four additional exterior cage curbs, vestibule, and rear walk.
-Electrical rough in ongoing.
-Continue welding Cage Run 26 vertical fence rails.
Recap of week ending January 10, 2025
-Poured and finished the first four of sixteen cage curb systems.
-Poured and finished concrete area from the fence to the existing slab.
-Insulated back flow preventer, tank inlet pipe, and building feed.
-Domestic water complete and tested with success.
-Began insulating interior plumbing.
-Cut building rough door openings.
-Pulled electrical circuits and mounted exterior lights.
-Fully welded all Cage Run 26 heater penthouse structures.
-Began fitting and welding Cage Run 26 vertical fence rails.
-Rough graded stockpiled spoils.