Sources of Noise

  • Hand tools.
  • Welding machines.

Utility Shutdowns

  • None at this time.

Deliveries

  • Equipment and materials.

Events for the upcoming week - R 23  

  • Fence contractor to start pulling the new roof chain fabric.
  • Offsite penthouse fabrication is ongoing.
  • Finish welding square tubing.

Recap of week ending September 19, 2025 - R 23

  • Mobilized equipment, materials, and tools to begin pulling roof chain.
  • Wheel sanded and applied cold galvanized paint to all welds.