TNPRC Cage Run 23 - Week of October 27, 2025

Sources of Noise

-Hand tools.
-Skid Steer.
-Welding machines.

Utility Shutdowns

-None currently.

Deliveries

-None currently.

Events for the upcoming week - R 23

-Install penthouse wall panels.
-Continue fully welding penthouse framing to enclosure rails.
-Tie wall chain fabric.

Recap of week ending October 24, 2025 - R 23

-Started fully welding penthouse framing to enclosure rails.
-Installed penthouse roofs.
-Continued wall chain ties.