Sources of Noise
- Hand tools.
- Skid Steer.
- Welding machines.
Utility Shutdowns
- None currently.
Deliveries
- None currently.
Events for the upcoming week - R 23
- Start plumbing gas main.
- Continue installing control panels, heater disconnect, and routing conduit.
- Schedule Vet Med and Design Team walk through.
Recap of week ending November 7, 2025 - R 23
- Finished wall panels excluding rear side for MEP construction access.
- Hung support struts and mounted heaters.
- Replaced wood perch material throughout the site.
- Started installing control panels, heater disconnect, and routing conduit.