Paul Hall - Week of October 14, 2022

Associated Project

Sources of Noise

  • Heavy Equipment
  • Demolition
  • Utility Vehicles
  • Power Tools

Utility Shutdowns:

  • None

Deliveries

  • Job trailers
  • Misc jobsite materials
  • Misc equipment
  • Concrete Trucks

Events for upcoming week

  • Continue install of Stair 2
  • Continue exterior sheathing
  • Begin fireproofing 6th floor
  • Continue steel tie in @ Flower Hall
  • Continue mechanical & electrical rough in
  • Continue work on Chilled Water & Steam
  • Continue framing walls on 3rd  & 4th floor

Recap of week performed (October 9th – October 15th  2022)

 

  • Started installing Stair 2
  • Continued fireproofing on 5th floor
  • Continued overhead rough-in on 2nd, 3rd & 4th floor
  • Continued work on Chilled Water & Steam @ S side
  • Continued framing walls on 2nd & 3rd floor