Paul Hall - Week of November 4, 2022

Associated Project

Sources of Noise

  • Heavy Equipment
  • Demolition
  • Utility Vehicles
  • Power Tools
  • Utility Shutdowns:

Deliveries

  • Job trailers
  • Misc jobsite materials
  • Misc equipment
  • Concrete Trucks

Events for upcoming week

  • Continue waterproofing
  • Continue brick install
  • Complete k-13 insulation
  • Complete  steel tie in @ Flower Hall
  • Continue mechanical & electrical rough in
  • Continue work on Chilled Water & Steam
  • Continue framing walls on 3rd , 4th  & 5th floor

Recap of week performed (November 6th – November 12th    2022)

  • Started brick install on N & W elevations
  • Continued steel tie in @ Flower Hall
  • Continued k-13 insulation on 3rd floor
  • Continued overhead rough-in on 2nd, 3rd & 4th floor
  • Continued work on Chilled Water & Steam @ S side
  • Continued framing walls on all levels