Paul Hall Cleanroom - Week of December 8, 2025

Sources of Noise

  • General Construction activities.

 

Utility Shutdowns

  • None at this time.

 

Deliveries 

  • 2nd round of Plenum unit deliveries begin on December 14, 2025

 

Events for upcoming week

  • Continue cleaning space.
  • Monitor space.
  • Complete CDA testing.
  • Begin receiving 2nd round of plenums.

 

Recap of Week ending December 7, 2025

  • Continue space cleaning.
  • Assemble additional platform extension.
  • Paul Lemestre site visit.
  • Site walk with THE to review low voltage install.
  • Install Compressed air line dryer unit.
  • Purge CDA lines for testing. System testing to be done by SSE.