Sources of Noise
- General Construction activities.
Utility Shutdowns
- None at this time.
Deliveries
- 2nd round of Plenum unit deliveries begin on December 14, 2025
Events for upcoming week
- Continue cleaning space.
- Monitor space.
- Complete CDA testing.
- Begin receiving 2nd round of plenums.
Recap of Week ending December 7, 2025
- Continue space cleaning.
- Assemble additional platform extension.
- Paul Lemestre site visit.
- Site walk with THE to review low voltage install.
- Install Compressed air line dryer unit.
- Purge CDA lines for testing. System testing to be done by SSE.