Paul Hall Cleanroom - Week of December 15, 2025

Sources of Noise

  • General Construction activities.

 

Utility Shutdowns

  • None at this time.

 

Deliveries 

  • 2nd round of Plenum unit deliveries begins December 14

 

Events for upcoming week

  • Continue cleaning space.
  • Monitor clean room protocol.
  • CDA testing results are expected (3-6 days from submission).
  • Continue 2nd round of plenum deliveries and installations.
  • Make connections to plenums that are installed for electrical and plumbing.

 

Recap of Week ending December 14, 2025

  • Continue space cleaning.
  • Prepare load platform for deliveries. Barricade the area.
  • Add ADA signage for Flower Hall access through Paul Hall.
  • End user meeting for progress discussion.
  • SSE conducted CDA line testing.
  • Submit CDA samples for analysis.
  • Begin 2nd round of plenum deliveries 14 Dec 2025.
  • Uncrate, wipe down, and bring plenums 5-9 inside clean room.
  • Mount plenums 5 and 6.
  • Prep electrical connections to plenums.