Sources of Noise
- General Construction activities.
Utility Shutdowns
- None at this time.
Deliveries
- 2nd round of Plenum unit deliveries begins December 14
Events for upcoming week
- Continue cleaning space.
- Monitor clean room protocol.
- CDA testing results are expected (3-6 days from submission).
- Continue 2nd round of plenum deliveries and installations.
- Make connections to plenums that are installed for electrical and plumbing.
Recap of Week ending December 14, 2025
- Continue space cleaning.
- Prepare load platform for deliveries. Barricade the area.
- Add ADA signage for Flower Hall access through Paul Hall.
- End user meeting for progress discussion.
- SSE conducted CDA line testing.
- Submit CDA samples for analysis.
- Begin 2nd round of plenum deliveries 14 Dec 2025.
- Uncrate, wipe down, and bring plenums 5-9 inside clean room.
- Mount plenums 5 and 6.
- Prep electrical connections to plenums.