Sources of Noise
-Exhaust fans
-Equipment
Utility Shutdowns
-None at this time.
Deliveries
-General construction equipment.
Events for upcoming week
-Continue MEP installation.
-Complete WT welded supports.
-Continue duct installation.
-Continue penthouse humidifier piping.
-Paint WT welds.
Recap of Week ending September 28, 2025
-Continue MEP installations.
-Add lighting fixtures at the high ceiling.
-Review AHU 5 cleaning requirements with contractor.
-Pressure test HVAC supply duct. Passed 9/25/25.
-Insulate penthouse duct humidifier section.
-Continue general site cleaning.