Sources of Noise
- General Construction activities.
Utility Shutdowns
- None at this time.
Deliveries
- General construction materials.
- HVAC cleaning items.
Events for upcoming week
- Particulate test of AHU 5 duct.
- Connect duct shaft to the supply duct.
- Patch wall openings from duct cleaning.
- Verify humidifier connections and functionality.
- Prep for flooring installation.
- Patch and paint clean room walls.
- Continue general site cleaning.
- We were notified that particulate test is delayed. Reschedule pending notification from tester.
Recap of Week ending October 26, 2025
- AHU 5 cleaned, Merv 17 filters installed, UV lights verified functional.
- AHU 5 duct cleaned from unit down to clean room.
- Made connections for humidifier power.
- Connected clean room power distribution panels to the transformer. 22 oct 2025.
- Clear unnecessary items from clean room.
- Confirm clean room layout for data, av, and telcom with Tip group.
- TBES check AHU and duct work for cleanliness before closing. Also verify filters and UV lights are installed/ functional.
- TBES performed Electrical torque verification on terminals.
- Scheduled particulate test for following week with duct connection and TAB to follow.
- Ultra high purity lines pressure tested and passed.