Paul Hall Clean Room - Week of October 27, 2025

Sources of Noise

  • General Construction activities.

Utility Shutdowns

  • None at this time.

Deliveries 

  • General construction materials.
  • HVAC cleaning items.

Events for upcoming week

  • Particulate test of AHU 5 duct.
  • Connect duct shaft to the supply duct.
  • Patch wall openings from duct cleaning.
  • Verify humidifier connections and functionality.
  • Prep for flooring installation.
  • Patch and paint clean room walls.
  • Continue general site cleaning.
  • We were notified that particulate test is delayed. Reschedule pending notification from tester.

Recap of Week ending October 26, 2025

  • AHU 5 cleaned, Merv 17 filters installed, UV lights verified functional.
  • AHU 5 duct cleaned from unit down to clean room.
  • Made connections for humidifier power.
  • Connected clean room power distribution panels to the transformer. 22 oct 2025.
  • Clear unnecessary items from clean room.
  • Confirm clean room layout for data, av, and telcom with Tip group.
  • TBES check AHU and duct work for cleanliness before closing. Also verify filters and UV lights are installed/ functional.
  • TBES performed Electrical torque verification on terminals.
  • Scheduled particulate test for following week with duct connection and TAB to follow.
  • Ultra high purity lines pressure tested and passed.