Sources of Noise
- General Construction activities.
Utility Shutdowns
- AHU shut down 21-23 Oct 2025 for cleaning.
- Transformer shutdown for clean room electrical connections 21-22 October 2025.
Deliveries
- General construction materials.
- HVAC cleaning items.
Events for upcoming week
- Continue MEP installation.
- Test DI water lines.
- Pressure test ultra-high purity water lines.
- Clean AHU 5 and duct down to clean room.
- Test duct airflow for particulates.
- Relocate Access control and CCTV camera wires into conduit.
- Run/ land electrical circuits to distribution panels.
- Continue general site cleaning.
Recap of Week ending October 26, 2025
- Prep duct shaft for cleaning activity.
- MEP above plenum adjustments.
- Verify UV bulbs were on site for AHU 5.
- End user meeting 16 Oct 2025.
- Continue general site cleaning.