Paul Hall Clean Room - Week of October 13, 2025

Sources of Noise

-General Construction activities.

Utility Shutdowns

-DI water shut down 13 October 2025.

Deliveries 

-General construction materials.

Events for upcoming week

-Continue MEP installation.
-Above Plenum inspections.
-Flush shaft process chill water lines.
-Review Plenum Delivery plan.
-Add conduit for wiring reroute.
-Relocate Access control and CCTV camera wires into conduit.
-Tie in the DI water lines to penthouse supply lines.
-Continue general site cleaning.

Recap of Week ending October 12, 2025

-Continue MEP installations.
-Complete duct welding.
-Flush process chill water lines.
-Paint WT weld plates.
-Complete plenum hangers.
-Continue general site cleaning.