Sources of Noise
- General Construction activities.
Utility Shutdowns
- None at this time.
Deliveries
- General construction materials.
- Flooring materials.
Events for upcoming week
- Build load platform for Plenum delivery.
- Coordinate plant removal from bed at clean room north exterior.
- Remove center window on North clean room wall.
- Protect window opening.
- Continue general site cleaning.
- Receive 1st plenum delivery.
Recap of Week ending November 16, 2025
- Tie in AHU supply duct to clean room duct.
- Complete floor level adjustments.
- Lay flooring in the Clean Room.
- Send alert for load platform.
- Lay down protective flooring.
- End user meeting 13 Nov 2025.
- Run Sensible chill water lines.
- Continue to review plenum delivery plan.