Sources of Noise
-Construction activities
-Vehicles
Utility Shutdowns
-None at this time.
Deliveries
-General Construction Materials
Events for upcoming week
-Broadmoor site mobilization.
-Place fence for lay down, restrooms, and dumpster.
-BIM coordination on going.
-Begin Surface prep.
-Begin Layouts
Recap of Week ending July 6, 2025
-Meet with Superintendent to discuss job logistics.
-Discuss restroom and dumpster location.
-Provide access card to Megan (Superintendent).
-OAC 1 July 2025.
-Place sign in sheet in clean room.