Paul Hall Clean Room - Week of January 26, 2026

Sources of Noise

  • General Construction activities.

Utility Shutdowns

  • None at this time.

Deliveries 

  • Sliding doors.

Events for upcoming week

  • Continue MEP installations with vent hood and wall rough in.
  • Continue Site cleaning.
  • Continue installing perimeter wall panels.
  • Install eye wash and emergency shower hardware at service bays 2 and 3.
  • Position hoods in clean room bays.
  • Secure service bay wire racks.
  • Monitor Cut station between Boggs and Flower Hall.
  • Engineer site visit.

Recap of Week ending January 25, 2026

  • Continue MEP installations with vent hood and wall rough in.
  • Continue Site cleaning.
  • Continue installing perimeter wall panels.
  • Install eye wash and emergency shower hardware at service bays 2 and 3.
  • Position hoods in clean room bays.
  • Adjust exhaust ducts.
  • Begin mounting service bay wire racks.
  • Prep wall mounts for sliding glass doors.
  • Complete service bay door installations.
  • Protect service bay doors.
  • Powers on site for controls installations.