Sources of Noise
- General Construction activities.
Utility Shutdowns
- None at this time.
Deliveries
- General construction materials.
Events for upcoming week
- Continue Plenum installations for units 1-4.
- Continue sprinkler system connections to plenum units being installed.
- Continue clean room protocol monitoring and continuous cleaning.
- Continue Sensible chill and process water line insulation.
- Begin installation of Plenum cooling coils.
Recap of Week ending November 30, 2025
- Insulate Sensible chill water lines in Penthouse.
- Load Plenums 1-4 into building using temp load zone. (23Nov2025)
- Adjust gowning area setup for hallway entry.
- Remove temp signage and stow load zone platforms and barricades after plenums inside.
- Make 1st Plenum fire sprinkler connection.
- Review lobby staging plan.