Paul Hall Clean Room - Week of December 1, 2025

Sources of Noise

  • General Construction activities.

Utility Shutdowns

  • None at this time.

Deliveries 

  • General construction materials.

Events for upcoming week

  • Continue Plenum installations for units 1-4.
  • Continue sprinkler system connections to plenum units being installed.
  • Continue clean room protocol monitoring and continuous cleaning.
  • Continue Sensible chill and process water line insulation.
  • Begin installation of Plenum cooling coils.

Recap of Week ending November 30, 2025

  • Insulate Sensible chill water lines in Penthouse.
  • Load Plenums 1-4 into building using temp load zone. (23Nov2025)
  • Adjust gowning area setup for hallway entry.
  • Remove temp signage and stow load zone platforms and barricades after plenums inside.
  • Make 1st Plenum fire sprinkler connection.
  • Review lobby staging plan.