Sources of Noise

-Air flow machines.
-Construction equipment warning sounds.

Utility Shutdowns

-Electrical Shut down 6 October 2025, 8am – 12 pm.

Deliveries 

-General construction Equipment

Events for upcoming week

-Continue MEP installations.
-Continue HVAC duct assembly welding.
-Add Breaker to 500kVa panel for clean room humidifier equipment.
-Continue AHU 5 duct humidifier installation.
-Make connections to penthouse DI skid for clean room equipment.


Recap of Week ending October 5, 2025

-Continue MEP installations.
-Install electrical conduits for duct humidifier.
-Install plenum Hangers.
-Continue hanging supply and vent duct work.
-Cut Supply duct for vent branches.
-Continue welding vent duct and adding dampers.