Sources of Noise
-Power tools: grinders, Hammer drills, chipping guns, etc...


Utility Shutdown
-N/A


Deliveries
-Framing material


Events for upcoming week
-Walls framed
-Holes cored for waste lines
-Floor penetrations filled
-3rd floor ceiling MEP and 5th floor pipe removal
-Plumbing layout

Recap of work performed (9/01//25 – 9/05/25)

-Filled floor penetrations
-Layout walls
-Framing material delivered 
-3RD floor demo 
-Courtyard landscape demo completed