Nursing L4 Aron - Week of October 27, 2025

Sources of Noise

-Power tools: grinders, Hammer drills, chipping guns, etc...

Utility Shutdown

-N/A

Deliveries

-Misc. material

Events for upcoming week

-Electrical rough-in and homeruns

-Insulating pipe and duct

-Prep for close wall inspection

Recap of work performed (10/20//25 – 10/25/25)

-Calmar spray insulation at exterior columns

-Domestic and heating hot water testing

-Insulating pipe and duct though-out all phases

-One side walls going up and prep for inwall inspection

-Duct installed for VAV’s