Nursing Aron L4 Renovation - Week of March 6, 2026

Sources of Noise

  • Power tools: grinders, Hammer drills, chipping guns, etc...


Utility Shutdown

  • N/A


Deliveries

  • N/A

 

Events for upcoming week

  • Sprinkler system finishes
  • Terrazzo grinding/NORA flooring install
  • Electric finish work and lighting install
  • Float, tape, finish, 1st coat walls
  • Casework install
  • Courtyard interior wall framing/window install
  • Plumbing finish work


Recap of work performed (2/23/26 – 2/27/26)

  • Casework delivery and install
  • Terrazzo prep and pour
  • Sanding, priming, and 1st coat painting continued
  • Ceiling grid install/framing
  • Courtyard demo resumed
  • Weather proofing of 4th floor Cleveland windows finished