College Track LaSalle Garage - Week of June 1, 2026

Sources of Noise

  • Power tools: grinders, Hammer drills, chipping guns, etc...

Utility Shutdowns

  • Sprinkler shutdown scheduled for Monday thru Wednesday this week

Deliveries

  • None

Events for the upcoming work week

  • ENFRA is working on getting AH-3 and AH-4 running this week, and installing air curtains in elevator lobby  
  • Marvins installing switches and getting ready to start trimming out all the fixtures 
  • CSI finishing up insulating 
  • King waiting to drop in the rest of the ceiling tiles once closed ceiling inspections are finalized 
  • Bonitz is skimming and prepping floors on the mezz to start installing by the end of the week 
  • CPC painting final coat throughout space.
  • DeGeorge is installing glass this week 
  • Custom cabinets will be delivering and starting the install of all cabinets throughout space this week 

Recap of work performed (May 25-29, 2026)

  • ENFRA worked on getting the AHU’s 3and 4 running, but it looks like it will be completed next week 
  • Marvins removed temporary lights and power as needed as well as started installing switches throughout space
  • CSI finishes up insulating throughout space   
  • King finished the drywall around the fire shutter and is working to get ceilings closed up 
  • Bonitz skimmed and laid the LVT on the first floor 
  • CPC installing final paint as needed