Associated Project
Sources of Noise
- Heavy Equipment
- Demolition
- Power Tools
Utility Shutdowns:
- None
Deliveries
- Misc jobsite materials
- Misc equipment
- Concrete Trucks
Events for upcoming week
- Continue New elevator install
- Prepping for transformer start up
- Layout & prep for lightning protection plan
- Continue installing steel @ old elevator shaft
- Continue stairwell fire door work
- Continue sprinkler riser rough in
- Continue misc MEP rough in
- Continue work on 2nd & 3rd floor
- Continue DOAS hook up
- Continue misc plaster repairs
Recap of week performed ( May 25th- May 30th 2026)
- Existing elevator demo complete
- Begin installing new elevator
- Continued stairwell openings for new fire doors
- Installing new elevator steel
- Continued misc plaster repairs
- Continued tape, float & prime 1st floor
- Continued misc MEP rough in