Sources of Noise
- Power tools: grinders, Hammer drills, chipping guns, etc...
Utility Shutdowns
- Sprinkler shutdown scheduled for everyday this week
Deliveries
- AHU’s have been delivered this morning on 4/27/26
Events for the upcoming work week
- ENFRA will be working on getting the pumps running filling up the new system with water and getting the units ready for startup
- Marvins working on getting power to the AHU’s and continuing to pull data lines
- CPC starting to paint final coat on the open baffle ceiling areas
- Powers running and hooking up control wires as needed
- King finishing the install of the Rako frames on the Mezz