Nursing Aron L4 Renovation - Week of March 13, 2026

Sources of Noise

  • Power tools: grinders, Hammer drills, chipping guns, etc...

Utility Shutdown

  • N/A


Deliveries

  • Casework, courtyard wall material


Events for upcoming week

  • Wellness room demo and cut/cap/make safe
  • Terrazzo grinding/NORA flooring install
  • Electric finish work and lighting install
  • Float, tape, finish, 1st coat walls
  • Casework install
  • Courtyard interior wall framing/window install
  • Plumbing finish work


Recap of work performed (3/02/26 – 3/06/26)

  • Casework install
  • Terrazzo grinding and prep
  • Sanding, priming, and 1st coat painting continued
  • Ceiling grid install/ framing
  • Courtyard demo
  • Electrical finishes