Sources of Noise
- Heavy Equipment
- Demolition
- Power Tools
Utility Shutdowns:
- None
Deliveries
- Misc jobsite materials
- Misc equipment
- Concrete Trucks
Events for upcoming week
- Complete switchgear installation
- Final in wall inspections
- Closing in walls on 1st floor
- Continue work @ 2nd & 3rd floor duct chases
- Continue layout & install of misc MEP
- Continue basement MEP re-route work
Recap of week performed (March 1 – March 7, 2026)
- Switchgear delivered & begin installation
- Continue above ceiling MEP on 1st floor
- Continued sprinkler pipe install on 1st floor
- Continued HVAC controls on 1st floor