Newcomb Hall First and Fourth Floor Renovation - Week of March 13, 2026

Sources of Noise

  • Heavy Equipment
  • Demolition
  • Power Tools

 

Utility Shutdowns:

  • None

 

Deliveries

  • Misc jobsite materials
  • Misc equipment
  • Concrete Trucks

 

Events for upcoming week

  • Complete switchgear installation
  • Final in wall inspections
  • Closing in walls on 1st floor
  • Continue work @ 2nd & 3rd floor duct chases
  • Continue layout & install of misc MEP
  • Continue basement MEP re-route work

 

Recap of week performed (March 1 – March 7, 2026)

  • Switchgear delivered & begin installation
  • Continue above ceiling MEP on 1st floor
  • Continued sprinkler pipe install on 1st floor
  • Continued  HVAC controls on 1st floor