Sources of Noise
- Construction Vehicles.
Utility Shutdowns
- None at this time.
Deliveries
- Construction Materials.
- Asphalt and dump trucks.
Events for the upcoming week
- Continue Tennis Surface installation
- Pave East tennis drive/ parking area.
- Weekend milling and paving of Broadway drive lane.
- Continue to backfill landscape areas.
- Add plants to landscape areas.
- Continue fence installation at Pine Street
- Continue low voltage/ data installations.
- Position Rest Room Trailer at SE Tennis courts.
- General site cleanup.
Recap of Week ending January 11, 2026
- Fill and cover Tennis Court expansion joints.
- Prep Court surface with levelers, cleaning, and base coating.
- Daktronics training. Equipment transferred to Athletics following training session.
- Architect walkthrough.
- Remove Pickleball court nets and handles and Transfer to Athletics.
- Add topsoil to landscaping beds.
- Continue expansion joint fill.
- Pressure wash tar spots from sidewalks and flatwork.
- Add meter box for future water North of Court two scoreboard near muscadine fence.
- Touch up asphalt joints at NW tennis parking area.
- Cover Backflow preventer with stainless box.
- Pour replacement concrete on South Sidewalk
- Begin fence installation at Pine Street lot fence.
- Remove bumpers along the drive lane from the Multispecialty clinic to Broadway St.
- Demo Perrier Street fencing and add caution tape.