Goldring Tennis and Pickleball Courts - Week of January 12, 2026

Sources of Noise

  • Construction Vehicles.

Utility Shutdowns

  • None at this time.

Deliveries 

  • Construction Materials.
  • Asphalt and dump trucks.

Events for the upcoming week

  • Continue Tennis Surface installation
  • Pave East tennis drive/ parking area.
  • Weekend milling and paving of Broadway drive lane.
  • Continue to backfill landscape areas.
  • Add plants to landscape areas.
  • Continue fence installation at Pine Street
  • Continue low voltage/ data installations.
  • Position Rest Room Trailer at SE Tennis courts.
  • General site cleanup.

Recap of Week ending January 11, 2026

  • Fill and cover Tennis Court expansion joints.
  • Prep Court surface with levelers, cleaning, and base coating.
  • Daktronics training. Equipment transferred to Athletics following training session.
  • Architect walkthrough.
  • Remove Pickleball court nets and handles and Transfer to Athletics.
  • Add topsoil to landscaping beds.
  • Continue expansion joint fill.
  • Pressure wash tar spots from sidewalks and flatwork.
  • Add meter box for future water North of Court two scoreboard near muscadine fence.
  • Touch up asphalt joints at NW tennis parking area.
  • Cover Backflow preventer with stainless box.
  • Pour replacement concrete on South Sidewalk
  • Begin fence installation at Pine Street lot fence.
  • Remove bumpers along the drive lane from the Multispecialty clinic to Broadway St.
  • Demo Perrier Street fencing and add caution tape.