Newcomb Hall First and Fourth Floor Renovation - Week of January 12, 2025

Sources of Noise

  • Heavy Equipment
  • Demolition
  • Power Tools

Utility Shutdowns:

  • None

Deliveries

  • Misc jobsite materials
  • Misc equipment
  • Concrete Trucks

Events for upcoming week

  • Form & pour transformer pad
  • Continue work @ light monitors
  • Continue installing duct
  • Continue layout & install of misc MEP
  • Continue layout & framing of 1st floor walls
  • Continue misc brick demo for shoring
  • Site cleanup, fencing repair, safety walk- prepping for student return

Recap of week performed (January 4- January 10)

  • Completed N light monitor opening
  • Continued layout & install of duct on 1st floor
  • Continued steel work @ light monitors
  • Poured pile caps @ transformer pad
  • Demoed corridor opening, clouds & plaster @ basement & 1st floor