TNPRC Cage Run 23 - Week of December 15, 2025

Sources of Noise

  • Hand tools.

 

Utility Shutdowns

  • None currently.
     

Deliveries

  • Materials and equipment.

 

Events for the upcoming week - R 23  

  • Complete wall patch modifications.
  • Train Tulane Facilities on Cage Run 23 MEP operations.
  • Continue removing tools, equipment, and materials.
  • Repair grade adjacent to the enclosure.
  • Pass magnet throughout the site for shards.

 

Recap of week ending December 12, 2025 - R 23

  • Commissioned MEP. No corrections required.
  • Installed penthouse access wall panels.
  • Vet Med approved the wall patch modification mockup.
  • Wall patch modifications are ongoing.
  • Delivered sand for grading swales.