Sources of Noise

  • Hand tools.

 

Utility Shutdowns

  • None Scheduled.

 

Deliveries

  • Second chute delivery expected this week.

 

Events for the upcoming week 

  • Unload squeeze chutes.
  • Mount squeeze chutes to the interior enclosures.
  • Install enrichment swivels.

 

Recap of week ending December 12, 2025

  • TBES Verified booster pump low suction safety for proper function.
  • Completed mounting the first delivery of squeeze chutes.