Goldring Tennis and Pickleball Courts - Week of December 15, 2025

Sources of Noise

  • Construction Vehicles.

 

Utility Shutdowns

  • None at this time.

 

Deliveries 

  • Construction Materials.
  • Asphalt and dump trucks.

 

Events for the upcoming week

  • Allow Tennis court to cure.
  • Prep NW parking lot and East Tennis drive lane subsurface for paving.
  • Continue Perrier Street fencing demo.
  • Continue fence installation at tennis courts.
  • Continue low voltage conduit installations.

 

Recap of Week ending December 14, 2025

  • Complete Tennis surface wearing course of asphalt.
  • Place University Square back on permanent water supply line.
  • Install fire suppression line back flow preventer.
  • Continue to fill expansion joints in the flatwork.
  • Prep umpire chair electrical infrastructure for the Tennis surface coating.
  • Add top and bottom rails to fencing.
  • Adjust bottom elevation of the Pickleball court fencing.
  • Remove fencing at Leake ave and pickleball courts.
  • Complete scorekeepers table outlet and data drop box installations.