Sources of Noise
- Construction Vehicles.
Utility Shutdowns
- None at this time.
Deliveries
- Construction Materials.
- Asphalt and dump trucks.
Events for the upcoming week
- Allow Tennis court to cure.
- Prep NW parking lot and East Tennis drive lane subsurface for paving.
- Continue Perrier Street fencing demo.
- Continue fence installation at tennis courts.
- Continue low voltage conduit installations.
Recap of Week ending December 14, 2025
- Complete Tennis surface wearing course of asphalt.
- Place University Square back on permanent water supply line.
- Install fire suppression line back flow preventer.
- Continue to fill expansion joints in the flatwork.
- Prep umpire chair electrical infrastructure for the Tennis surface coating.
- Add top and bottom rails to fencing.
- Adjust bottom elevation of the Pickleball court fencing.
- Remove fencing at Leake ave and pickleball courts.
- Complete scorekeepers table outlet and data drop box installations.